Time for submittals Sample Clauses

Time for submittals. Each submittal must be received by the A-E in time to permit 21calendar days for their review. If a submittal is not received in time to allow sufficient time, (calendar days) for the A-E's review without delaying construction, the ▇▇▇▇ shall reimburse Owner for the A-E's costs incurred by checking on an accelerated basis.
Time for submittals. Each submittal must be received by the A-E in time to permit (14) calendar days for their review. If a submittal is not received in time to allow sufficient time, (fourteen calendar days) for the A-E's review without delaying construction, the Contractor shall reimburse County for the A- E's costs incurred by checking on an accelerated basis. (1) The A-E's or County’s responsibility for time consumed in review of construction data and any claim made by the Contractor (including Subcontractors and suppliers) that such time is excessive and has caused or will cause delay in completion of the work, will only be considered as starting from the time drawings, samples and other construction data are complete and correct in all respects and so submitted and signed as approved by Contractor. (2) Preliminary and incomplete or incorrect submittals of said drawings and samples shall not be considered as the beginning of the official approved time.
Time for submittals. Each submittal must be received by the A-E in time to permit at least 21 calendar days for their review. If a submittal is not received in time to allow at least 21 calendar days for the A-E's review without delaying construction, the CMARE shall reimburse County for the A-E's costs incurred by checking on an accelerated basis.
Time for submittals. (i) Except as otherwise explicitly provided in the D&C Schedule of Submittals or this Design-Build Contract, the Design-Builder will obtain and submit to the Developer all documentation required to make the Submittals as described under Section 8.1 to the Developer (1) where a time is prescribed in the Lease or such other DB Project Document to make such Submittal, within no more than eighty percent (80%) of the time period provided to the Developer, or (2) where no time period is prescribed, in a timely fashion to permit Developer review, but, in the case of clauses (1) and (2), in any event no later than five (5) Business Days prior to the date such Submittal is due under the Lease or such other DB Project Document, as applicable; provided, however, if any Submittals are required to be delivered to the Port Authority within less than five (5) Business Days of the occurrence of the event that gives rise to such Submittals, the Developer shall authorize the Design-Builder to deliver such Submittals to the Developer and, on behalf of the Developer, to the Port Authority concurrently to ensure timely receipt by the Port Authority thereof. The Parties shall agree and maintain a list of the type of Submittals which are so authorized. (ii) If no time period is specified in the Lease or such other DB Project Document with respect to submission of a Submittal, the Design-Builder shall (1) designate in writing to the Developer a DB Requested Submission Date for such Submittal, and (2) obtain and submit to the Developer all documentation required to make the applicable Submittal as described under Section 8.1 by the date no later than five (5) Business Days prior to the DB Requested Submission Date. The Submittal shall be made by the Developer to the Port Authority no later than the DB Requested Submission Date or, if no date is stipulated, within five (5) Business Days. (iii) Subject to receipt of timely Submittals from the Design-Builder pursuant to this Section 8.3(a) and as required by this Design-Build Contract and the other DB Project Documents, the Developer will submit each Submittal made under the Project Documents to the Port Authority or the Lenders, as applicable, (1) within the time period required, if any, by the provisions of the Lease, the D&C Schedule of Submittals, the Requirements and Provisions for Work and the other provisions of the DB Project Documents or (2) if no time period is specified in the Lease, the D&C Schedule of Submittals, the Req...