Time Extension Requests Sample Clauses
The Time Extension Requests clause allows a party, typically a contractor, to formally request additional time to complete contractual obligations when delays occur. This process usually requires the requesting party to submit a written notice detailing the reasons for the delay, such as unforeseen site conditions or changes in project scope, along with supporting documentation. By establishing a clear procedure for handling delays, the clause helps prevent disputes over project timelines and ensures that both parties have a mutual understanding of how schedule adjustments are managed.
Time Extension Requests. CM shall review, verify, and recommend approval/rejection of Contractor requests for time extension for merit and quantum. CM shall participate in the negotiation of time extension requests with the Contractor and JWA. CM shall process change orders for time through the JWA Skire Unifier System.
Time Extension Requests. Any time extension shall be requested within 21 days after the Contractor knew or should have known about the delay and shall be supported by the critical path schedule analysis.