The Owner's Right to Carry Out the Work Sample Clauses

The Owner's Right to Carry Out the Work clause grants the project owner the authority to take over and complete the contractor's obligations if the contractor fails to perform as required. In practice, this means that if the contractor is not meeting deadlines, quality standards, or other contractual requirements, the owner can step in, hire others, or use their own resources to finish the work. This clause ensures that the project can continue without undue delay and protects the owner from losses caused by contractor default or non-performance.
POPULAR SAMPLE Copied 1 times
The Owner's Right to Carry Out the Work. If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within five (5) days after receipt of written notice from the Owner to commence and correct such default or neglects to carry out the Work with diligence and promptness, the Owner may, without affecting any other remedy the Owner may have, correct any such deficiencies. In such case, an appropriate Change Order shall be issued deducting from the payments then or thereafter due the Contractor the cost of correcting any such deficiencies, including without limitation, architectural, consulting and legal fees required by the circumstances. If the payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor shall pay the difference to the Owner.
The Owner's Right to Carry Out the Work. 2.4.1 If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within a seven (7) day period after receipt of written notice from the Owner to commence and continue correction of such default or neglect with diligence and promptness, the Owner may after such 7-day period, without prejudice to other remedies the Owner may have, correct such deficiencies. In such case, the Owner shall have the right to offset and deduct from payments then or thereafter due the Contractor the cost correcting such deficiencies, including compensation for the Architect's additional services and expenses made necessary by such default, neglect or failure. If payments then or thereafter due the Contractor are not sufficient to cover such amounts, the Contractor shall pay immediately the difference to the Owner.

Related to The Owner's Right to Carry Out the Work

  • OWNER’S RIGHT TO CARRY OUT THE WORK If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within a ten (10)-calendar day period after receipt of written notice from the Owner to commence and continue correction of such default or neglect with diligence and promptness, the Owner may, without prejudice to other remedies the Owner may have, correct such deficiencies. In such case an appropriate Change Order shall be issued deducting from payments then or thereafter due the Contractor the reasonable cost of correcting such deficiencies, including Owner’s expenses and compensation for the Architect’s additional services made necessary by such default, neglect or failure. Such action by the Owner and amounts charged to the Contractor are both subject to prior approval of the Architect. If payments then or thereafter due the Contractor are not sufficient to cover such amounts, the Contractor shall pay the difference to the Owner.

  • STATE'S RIGHT TO CARRY OUT THE WORK 3.4.1 If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within seven days after receipt of written notice from the State to commence and continue correction of such default or neglect with diligence and promptness, the State may, after seven days following receipt by the Contractor of an additional written notice and without prejudice to any other remedy he may have, make good such deficiencies. In such case an appropriate Change Order shall be issued deducting from the payments then or thereafter due the Contractor the cost of correcting such deficiencies, including compensation for the Architect's and the State’s additional services made necessary by such default, neglect or failure. Such action by the State and the amount charged to the Contractor are both subject to review by the Architect under Paragraph 2.2.14 of these General Conditions. If the payments then or thereafter due the Contractor are not sufficient to cover the amounts paid by the State to make good such deficiencies, then the Contractor shall pay the difference to the Owner.

  • Owner’s Right to Stop Work The Owner reserves the right, for itself and for any designated Construction Inspector retained by Owner, upon observation of apparent nonconforming Work, to immediately stop the affected Work. If the Work is later determined by the Design Professional to be in fact conforming Work, then Contractor shall be entitled upon timely claim to a Change Order for payment by Owner of any reasonable Actual Costs actually incurred by Contractor in connection with the stop Work order and resumption of the Work, as well as an extension in the time for performance of the Work to the extent Contractor is delayed by Owner's stop Work order. The Design Professional shall determine the time, which shall be binding upon both Owner and Contractor, as set forth in Section 3, Part 3.

  • STATE'S RIGHT TO STOP THE WORK 3.3.1 If the Contractor fails to correct defective Work as required by Paragraph 13.2 or persistently fails to carry out the Work in accordance with the Contract Documents, the State, by a written order signed personally or by an agent specifically so empowered by the State in writing, may order the Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of the State to the stop the Work shall not give rise to any duty on the part the State to exercise this right for the benefit of the Contractor or any other person or entity, except to the extent required by Subparagraph 6.1.3.

  • BUYER’S RIGHT TO CANCEL If after completion of an appraisal by a licensed appraiser, Buyer receives written notice from the Lender or the appraiser that the Property has appraised for less than the Purchase Price (a “Notice of Appraised Value”), Buyer may cancel the REPC by providing written notice to Seller (with a copy of the Notice of Appraised Value) no later than the Financing & Appraisal Deadline referenced in Section 24(c); whereupon the ▇▇▇▇▇▇▇ Money Deposit shall be released to Buyer without the requirement of further written authorization from Seller.