TESTS SCHEDULE Sample Clauses

TESTS SCHEDULE. For information purposes Contractor will provide Commission its definite Tests Schedule and the date when these are planned to begin, at least sixty (60) Days before those scheduled activities. Contractor will also notify Commission that it intends to perform the Tests required for the Station at least fifteen (15) Days before the date when it actually pretends to carry them out. Within four (4) Days after receiving aforementioned notification, Commission will notify Contractor that it is in a condition to receive the power generated during the Tests in a manner compatible with prudent practice in industry. If Commission is not able to receive the power on the date proposed, Commission will put forth all reasonable efforts to obtain a solution for this as soon as possible and as reasonably practical under the circumstances. Contractor will not be applied a penalty according to this Contract for not complying with the Critical Event Dates related to