Common use of System Acceptance Testing Clause in Contracts

System Acceptance Testing. (a) Provider shall conduct testing of the System in accordance with such methods, acts, guidelines, standards and criteria reasonably accepted or followed by commercial solar photovoltaic energy system integrators and operators in the United States. (b) If the results of such testing indicate that the System is capable of generating Energy for at least four (4) consecutive hours, using such instruments and meters as have been installed for such purposes, and the System has been approved for interconnected operation by the Local Electric Utility and any other Governmental Authority from whom approval is required to operate the System, then Provider shall send a written notice to Purchaser to that effect, and the date of such notice shall be the “Commercial Operation Date.”

Appears in 6 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement