Startup Deadline Sample Clauses

The Startup Deadline clause sets a specific date or timeframe by which a project, service, or business operation must commence. In practice, this clause applies to contracts where timely initiation is critical, such as construction projects, software deployments, or business partnerships, and may include consequences if the deadline is missed, like penalties or termination rights. Its core function is to ensure all parties are aligned on when activities must begin, thereby reducing uncertainty and helping to manage expectations and project timelines.
Startup Deadline. The Startup Deadline is [Date], or such other date as provided in this Agreement; provided that, notwithstanding anything herein to the contrary, the Startup Deadline may not be later than five (5) years from the Effective Date. Subject to the foregoing, the Startup Deadline shall be extended on a day-for-day basis for any delay in enactment of the Federal Investment Tax Credit Legislation beyond [Date].
Startup Deadline. The Startup Deadline shall be the date which is twenty-four (24) months after the Trigger Date, but in no event later than December 31, 2013 or as may be agreed to in a writing signed by both Parties. The Startup Deadline shall be extended on a day-for-day basis for any Force Majeure event in accordance with Section 5.03 or for any delays in construction under an agreement for transmission and interconnection access with respect to the Generating Facility which are not caused or contributed to by Seller.
Startup Deadline. The Startup Deadline shall be May 15, 2009 plus any additional days for Force Majeure as provided in Section 5.03, or such other date as provided in this Agreement or as may be agreed to in a writing signed by both Parties; provided that Seller shall use reasonable commercial efforts to achieve an earlier startup of December 15, 2008.
Startup Deadline. The Startup Deadline shall be the date which is the later of (i) thirty-six (36) months after the Trigger Date and (ii) three (3) months after the Transmission Completion Date, but in no event later than twelve (12) months after the Forecasted Initial Operation Date, or as may be agreed to in a writing signed by both Parties. Subject to the foregoing, the Startup Deadline shall be extended on a day-for-day basis for any: (i) lapse or repeal of the Federal Investment Tax Credit Legislation that occurs at any time on or before the date that is twenty-four (24) months prior to the Forecasted Initial Operation Date, (ii) Force Majeure event, (iii) Event of Default of SCE which directly impairs or affects the ability of Seller to achieve the Startup Deadline; or (iv) delay in construction under an agreement for transmission and interconnection access with respect to the Generating Facility, which is not caused or contributed to by Seller; provided that in no case shall the Startup Deadline be extended beyond twelve (12) months after the Forecasted Initial Operation Date.
Startup Deadline. The startup deadline for delivering energy to the Delivery Point shall be September 30, 2009 (the “Startup Deadline”), plus any additional days for Force Majeure as provided in Section 5.03, or such other date as provided in this Agreement or as may be agreed to in a writing signed by both Parties; provided that Seller shall use reasonable commercial efforts to achieve an earlier startup of December 15, 2008.
Startup Deadline. The Startup Deadline cannot be later than five (5) years from the Effective Date of the PPSA.
Startup Deadline. The Startup Deadline shall be [Date], or such other date as provided in this Agreement or as may be agreed to in writing signed by both Parties.