Shift Time-Construction Work. When the owner of a job or jobs desires to work the Employees of all crafts employed on the aforementioned job or jobs for ten (10) hours on four (4) consecutive days rather than eight (8) hours on five (5) consecutive days, Employees will be allowed to do so at the straight time wage under the following stipulations:
1. The four (4) consecutive days shall be either Monday through Thursday or Tuesday through Friday with all Employees on a job working the same four (4) days;
2. There shall be no fifth day “make up day”, regardless of the reason for any interruption on the four (4) consecutive days;
3. Any work performed in excess of ten (10) hours per day on any of the ten (10) hour work days will be paid at one and one-half (1 ½ ) times the base wage as shall any work performed on a Monday or Friday which is not a part of the assigned four (4) day/ten (10) hours per day work week (until such time as the Employee is reassigned, in advance, to a regular Monday through Friday – eight (8) hour per day work week) and any work performed on Saturdays. Any work performed on Sundays and Holidays will be at two (2) times the base wage.
4. A request to work under the above conditions shall be submitted to the Business Manager before any job begins.
Shift Time-Construction Work. When two (2) shifts are employed for a period of five (5) consecutive days or more, the shift Employed between the hours of 8:00 a.m. and 4:30 p.m. shall receive the regular rate of pay and shall be identified as the First (1st) Shift. The Second (2nd) Shift will be between the hours of 4:30 p.m. and 1:00 a.m. Floating starting time may apply as in Section 2.2. of this Article.