Scope of Facilities Study Sample Clauses

Scope of Facilities Study. The Facilities Study shall update and refine the description of Network Upgrade Facilities identified in the System Impact Study, including the equipment, work and related cost and time estimates necessary to construct the required Network Upgrade Facilities. Transmission Developer will be responsible for posting Security in the amount of the cost estimates for the Network Upgrade Facilities documented in the final Facilities Study report pursuant to Section
Scope of Facilities Study. The Facilities Study shall specify the nature of, and estimate the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the System Impact Study in accordance with Good Utility Practice to physically and electrically connect the Generating Facility to the IPA Switchyard. The Facilities Study may identify any necessary Network Upgrades and shall identify (i) the electrical switching configuration of the connection equipment, including, without limitation, the transformer, switchgear, meters, and other station equipment; (ii) the nature and estimated cost of any IPA Interconnection Facilities necessary to accomplish the interconnection; and (iii) an estimate of the time required to complete the construction and installation of such facilities.
Scope of Facilities Study. ‌ The Facilities Study shall specify the nature of, and estimate the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the System Impact Study in accordance with Good Utility Practice and NERC/WECC reliability standards to physically and electrically connect the Generating Facility to the IPA Switchyard. The Facilities Study may identify any necessary Network Upgrades and shall identify (i) the electrical switching configuration of the connection equipment, including, without limitation, the transformer, switchgear, meters, and other station equipment; (ii) the nature and estimated cost of any IPA Interconnection Facilities necessary to accomplish the interconnection; and (iii) an estimate of the time required to complete the construction and installation of such facilities. The Facilities Study will also identify any potential control equipment for requests for Interconnection Service that are lower than the Generating Facility Capacity.
Scope of Facilities Study. The Facilities Study shall update and refine the description of Network Upgrade Facilities identified in the System Impact Study, including the equipment, work and related cost and time estimates necessary to construct the required Network Upgrade Facilities. Transmission Developer will be responsible for posting Security in the amount of the cost estimates for the Network Upgrade Facilities documented in the final Facilities Study report pursuant to Section 22.11.1 of this Attachment P. The Facilities Study shall also contain a non‑binding estimate as to the feasible TCCs resulting from the construction of the new facilities, as applicable.