Schedule progress Sample Clauses

Schedule progress. The contractor shall prepare an activity weighted average report that apportions a dollar amount for each activity in the performance schedule (“AWA Report”). An AWA Report shall be prepared by the contractor and submitted to the COTR in conjunction with the Performance Schedule (7) days after contract award.
AutoNDA by SimpleDocs
Schedule progress. Time is of the essence of this Subcontract. Subcontractor agrees to commence and complete the Work as directed by Contractor in accordance with the timeline as set by the Contract Documents (Schedule) and so as not to delay Contractor, Owner or other contractors or subcontractors. Subcontractor shall promptly increase its work force, accelerate its performance, work overtime, including Saturdays, Sundays and holidays, all without additional compensation if, in the opinion of Contractor, such work is necessary to maintain proper progress. No premium time will be paid unless authorized in writing by Contractor. If Subcontractor is responsible for any delay in the Schedule, Subcontractor shall pay Contractor for all costs and damages suffered by Contractor as a result of such delays, including, but not limited to, any actual or liquidated damages assessed against Contractor.

Related to Schedule progress

  • Progress Schedule The Contractor, within ten (10) working days of receiving notice of the award of the contract, shall prepare and submit for the State's and Architect's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

  • Construction Progress Schedule A schedule indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion and Occupancy and Final Completion. The schedule will be developed to represent the sixteen or seventeen CSI Specification Divisions. It shall have a minimum number of activities as required to adequately represent to Owner the complete scope of work and define the Project’s critical path and associated activities. If the Project is to be phased, then each individual Phase should be identified from start through completion of the overall Project and should be individually scheduled and described, including any Owner’s occupancy requirements and showing portions of the Project having occupancy priority. The format of the schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, Material Completion and Occupancy Date, final inspection dates, Punchlist, and Final Completion date.

  • Work Schedule Changes 215. It is agreed that pursuant to the exercise of management rights, normal work schedules may be changed without mutual agreement, subject to compliance with other provisions of this Agreement. However, it is agreed that the effects of consequences of such changes are subject to the meet and confer obligation to the extent required by state law.

  • Schedule C Schedule C to the Agreement, setting forth the Portfolios of the Trust on behalf of which the Trust is entering into the Agreement, is hereby replaced in its entirety by Schedule C attached hereto.

  • Schedule Changes Employees’ workweeks and work schedules may be changed with prior notice from the Employer. Overtime-eligible employees shall receive fourteen (14) calendar days’ written notice of a permanent schedule change. Employees shall receive seven (7) calendar days’ notice of a temporary schedule change. A temporary schedule change is defined as lasting thirty (30) days or less. The day notification is given is considered the first day of notice. Adjustments in the hours of work of daily work shifts during a workweek do not constitute a schedule change. The Employer may adjust an overtime-eligible employee’s daily start and/or end time(s) by two (2) hours.

  • Contract Schedule The information set forth in the Contract Schedule is true and correct.

  • COMPLETION SCHEDULE 6.1 The proposed schedule for the completion of the Project is presented in “Attachment D” and is made a part hereof.

  • Work Authorization Budget A work authorization budget shall set forth in detail (1) the computation of the estimated cost of the work as described in the work authorization, (2) the estimated time (hours/days) required to complete the work at the hourly rates established in Attachment E, Fee Schedule; (3) a work plan that includes a list of the work to be performed, (4) a stated maximum number of calendar days to complete the work, and (5) a cost-not-to-exceed-amount or unit or lump sum cost and the total cost or price of the work authorization. The State will not pay items of cost that are not included in or rates that exceed those approved in Attachment E.

  • Development Schedule The Project shall substantially comply with the specific timetables and triggers for action set forth in Article 5 of this Agreement. The parties acknowledge that, as provided in G.S. 160A-400.25(b), the failure to meet a commencement or completion date shall not, in and of itself, constitute a material breach of this Agreement pursuant to G.S. 160A-400.27 but must be judged based upon the totality of the circumstances.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

Time is Money Join Law Insider Premium to draft better contracts faster.