Schedule progress Clause Samples

Schedule progress. The contractor shall prepare an activity weighted average report that apportions a dollar amount for each activity in the performance schedule (“AWA Report”). An AWA Report shall be prepared by the contractor and submitted to the COTR in conjunction with the Performance Schedule (7) days after contract award.
Schedule progress. Time is of the essence of this Subcontract. Subcontractor agrees to commence and complete the Work as directed by Contractor in accordance with the timeline as set by the Contract Documents (Schedule) and so as not to delay Contractor, Owner or other contractors or subcontractors. Subcontractor shall promptly increase its work force, accelerate its performance, work overtime, including Saturdays, Sundays and holidays, all without additional compensation if, in the opinion of Contractor, such work is necessary to maintain proper progress. No premium time will be paid unless authorized in writing by Contractor. If Subcontractor is responsible for any delay in the Schedule, Subcontractor shall pay Contractor for all costs and damages suffered by Contractor as a result of such delays, including, but not limited to, any actual or liquidated damages assessed against Contractor.

Related to Schedule progress

  • PROGRESS SCHEDULE The Contractor, within ten (10) working days of receiving notice of the award of the contract, shall prepare and submit for the State's and Architect's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

  • Construction Progress Schedule A schedule indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion and Occupancy and Final Completion. The schedule will be developed to represent the sixteen or seventeen CSI Specification Divisions. It shall have a minimum number of activities as required to adequately represent to Owner the complete scope of work and define the Project’s critical path and associated activities. If the Project is to be phased, then each individual Phase should be identified from start through completion of the overall Project and should be individually scheduled and described, including any Owner’s occupancy requirements and showing portions of the Project having occupancy priority. The format of the schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, Material Completion and Occupancy Date, final inspection dates, Punchlist, and Final Completion date.

  • Schedule C SUBADVISORY FEE

  • Schedule Changes (a) If, in the course of a posted schedule, the Employer: (i) changes Employees’ scheduled days off without giving 14 days’ notice of the change, they shall be paid 2X their Basic Rate of Pay for all hours worked on what would otherwise have been their off-duty days. (ii) changes Employees’ scheduled Shift, but not their scheduled days off, without giving 14 days’ notice of the change, they shall be paid 2X their Basic Rate of Pay for all hours worked during the first Shift of the changed schedule. (b) Employees shall be notified of such changes in their schedule and such changes shall be recorded on the Shift schedule. (c) An Employee or the Employer may, during the course of a posted schedule, ask to amend scheduled Shifts. Such Employee requests shall be granted where operationally possible without additional cost. Where mutually agreed, the requirements for 14 days’ notice of change and the resultant penalty pay as described in Article 7.04(a) shall not apply. Employees or the Employer should make such requests as far in advance as possible in order to maximize the ability to accommodate the request. Any Shift changes made by mutual agreement shall not violate the scheduling provisions of this Article.

  • Contract Schedule The information set forth in the Contract Schedule is true and correct.