Schedule for Base Building Work Clause Samples
Schedule for Base Building Work. Once City of San Francisco Planning Department approval for the remaining Base Building Work is secured, Landlord and Tenant shall mutually agree upon a schedule of milestones and remedies as they relate to Landlord’s construction permits and completion of the Base Building Work.
Schedule for Base Building Work. The Base Building Construction Schedule is attached as Rider 1 to this Work Letter (“Base Building Construction Schedule”). The Base Building Construction Schedule contains certain assumptions on which it is based. If the actual conditions or circumstances deviate from such assumptions, Landlord may from time to time reasonably adjust the Base Building Work Schedule in a manner consistent with such deviation and shall promptly notify Tenant of any material adjustment, provided that such adjustment does not change the Target Commencement Date.