Common use of Schedule Control Clause in Contracts

Schedule Control. The GC shall be wholly responsible for the schedule and ensuring the project schedule is maintained and executed. The GC shall generate a baseline CPM schedule and monthly CPM schedule updates. The CMA is required to: 1. Continuously monitor actual progress against the Project Schedule and identify any delays or potential delays. If the CMA observes or anticipates delays, it is required to recommend recovery actions to APS’s Project Manager 2. Review and provide comment on the Project CPM Schedule, monthly CPM Schedule Updates, and Recovery Schedules. The CMA shall also provide recommendations for delay mitigation, if necessary.