Request For Time Extension Sample Clauses

Request For Time Extension. Any request for time extension or additional compensation shall be made in accordance with ARTICLE 28, CLAIM NOTICE AND RESOLUTION PROCEDURE.
AutoNDA by SimpleDocs
Request For Time Extension. Any request for time extension or additional compensation shall be made in accordance with ARTICLE 37, CLAIM NOTICE AND RESOLUTION PROCEDURE. If, at any time, Company determines the progress of the Work is unsatisfactory, Contractor may be directed to work overtime, increase its workforce, work additional shifts, add supervision or take other corrective actions to ensure the timely and orderly prosecution of the Work, at no additional cost to Company. SITE INVESTIGATION Contractor represents it has reviewed the O&M Procedures Manuals made available to Contractor by Company (including all technical information letters (TILs)) and that such O&M Procedures Manuals fully and completely describe the proper operation and maintenance of the Wind Projects. Contractor represents it has satisfied itself as to the nature and location of the Work, the general, local, physical and other conditions of the Work, particularly those bearing upon: transportation, access, disposal, handling and storage of materials, availability and quality of labor, water, electric power, roads, uncertainties of weather, including flash floods and other physical conditions at the Work Site(s), the character of conditions on the ground, the character, quality and quantity of surface and subsurface material to be encountered, the character of equipment and facilities needed preliminary to and during the prosecution of the Work, and all other matters which could in any way affect the Work or the cost thereof under this Contract. The failure of Contractor to adequately investigate and acquaint itself with the available information concerning these conditions and all other matters which could in any way affect the Work or the cost thereof under this Contract shall not relieve Contractor from its responsibility for properly estimating the difficulties and costs of successfully performing the Work and completing this Contract, and shall not be grounds for adjusting either the price or the schedule. Company assumes no responsibility for any understanding or representation made by any of its officers or agents during or prior to the negotiations and execution of this Contract.
Request For Time Extension. Any request for time extension or additional compensation shall be made in accordance with ARTICLE , CLAIM NOTICE AND RESOLUTION PROCEDURE. If, at any time, Owner determines the progress of the Work is unsatisfactory, Contractor may be directed to work overtime, increase its workforce, work additional shifts, add supervision or take other corrective actions to ensure the timely and orderly prosecution of the Work, at no additional cost to Owner.
Request For Time Extension. In the event the Contractor requests an extension of Contract Time for unavoidable delay, the Contractor shall furnish such justification and supporting evidence as the AOC may deem necessary for the determination as to whether the Contractor is entitled to an extension of Contract Time. The Contractor shall submit justification no later than 7 days after the initial occurrence of any delay. The justification shall be based on the Official Progress Schedule as updated at the time of occurrence of the delay or execution of work related to any changes to the scope of the Work. The justification shall include, but is not limited to the following information:
Request For Time Extension. Either party may request in writing and receive extensions of the time limits prescribed above.

Related to Request For Time Extension

  • Time Extension CONTRACTOR shall provide a time extension request on completion of Task Order for delays caused by others (Permitting Agencies, COUNTY or Contract Cities, or unforeseen conditions such as inclement weather, etc.) and at no fault by CONTRACTOR, subject to approval by COUNTY. COUNTY will review the request and determine in its sole discretion whether the situation warrant a time extension at no-cost or with costs. If CONTRACTOR completes the Task Order beyond the stipulated completion date without COUNTY’s specific written approval for time extension, CONTRACTOR will be subject to liquidated damages and may be construed as non-responsive, which may affect CONTRACTOR for considerations for future Task Orders or projects.

  • Request for Extension Upon request, the Department may extend the time allowed for both a response to the Letter of Concern and a Corrective Action Plan depending upon the nature of the deficiency. The Provider shall request an extension of time in writing from the Department’s designated representative. The written request shall contain a justification and proposed extension period.

  • Renewal, Extension The renewal or extension of any Letter of Credit shall, for purposes hereof, be treated in all respects the same as the issuance of a new Letter of Credit hereunder.

  • Notice of Extension (a) If the Institutional Trustee is the only registered Holder at the time the Company selects an Extended Interest Payment Period, the Company shall give written notice to the Regular Trustees, the Institutional Trustee and the Trustee of its selection of such Extended Interest Payment Period one Business Day before the earlier of (i) the next succeeding date on which Distributions on the Trust Securities issued by the Trust are payable, or (ii) the date the Trust is required to give notice of the record date, or the date such Distributions are payable, to the New York Stock Exchange or other applicable self-regulatory organization or to holders of the Preferred Securities issued by the Trust, but in any event at least one Business Day before such record date.

  • Listing Period Extension The Commission shall be due if the Property is sold, conveyed, exchanged, optioned, or otherwise transferred within _ _ days (“Extension Period”) after the expiration of the Listing Period to anyone with whom the Broker or Agency has negotiated unless the Property is listed, in good faith, with another real estate agency. The term “negotiation” shall include providing information about the Property, showing the Property, or presenting an offer on the Property. All rights under this Section shall terminate upon the expiration of the Extension Period.

  • Request for Waiver A. Prior to submission of a request for a partial or total waiver, Bidder/Contractor shall speak to the Designated Contacts of the OGS Office of Minority- and Women-Owned Business Enterprises for guidance.

  • Request for Leave At any time, employees may request the use of short-term leave (annual leave, compensatory time use, or personal leave). Such request shall be submitted on the appropriate form and approved or denied on the form within one week of submission to the appropriate authority (practices of shorter time periods will be maintained) except that current practices concerning emergency leave requests shall be maintained. Requests will not be denied unreasonably. The issue of more employees requesting the use of short-term leave than can be granted because of operational needs shall be resolved at the LMC. The Employer shall not request the reasons for the use of earned leave other than sick leave as permitted by Article 12. All leave may be used in tenth of an hour increments provided, however that use of personal leave to cover tardiness related absences shall not serve as a bar or defense to disciplinary action.

  • Requesting Price Increase/Required Documentation Contractor must submit a written notification at least thirty (30) calendar days prior to the requested effective date of the change, setting the amount of the increase, along with an itemized list of any increased prices, showing the Contractor’s current price, revised price, the actual dollar difference and the percentage of the price increase by line item. Price change requests must include H-GAC Forms D Offered Item Pricing and E Options Pricing, or the documentation used to submit pricing in the original Response and be supported with substantive documentation (e.g. manufacturer's price increase notices, copies of invoices from suppliers, etc.) clearly showing that Contractor's actual costs have increased per the applicable line item bid. The Producer Price Index (PPI) may be used as partial justification, subject to approval by H-GAC, but no price increase based solely on an increase in the PPI will be allowed. This documentation should be submitted in Excel format to facilitate analysis and updating of the website. The letter and documentation must be sent to the Bids and Specifications manager, Xxxxxxx Xxxxxx, at Xxxxxxx.Xxxxxx@x-xxx.xxx Review/Approval of Requests If H-GAC approves the price increase, Contractor will be notified in writing; no price increase will be effective until Contractor receives this notice. If H-GAC does not approve Contractor’s price increase, Contractor may terminate its performance upon sixty (60) days advance written notice to H-GAC, however Contractor must fulfill any outstanding Purchase Orders. Termination of performance is Contractor’s only remedy if H-GAC does not approve the price increase. H-GAC reserves the right to accept or reject any price change request.

  • Determination to Honor Drawing Request In determining whether to honor any request for drawing under any Letter of Credit by the beneficiary thereof, Agent shall be responsible only to determine that the documents and certificates required to be delivered under such Letter of Credit have been delivered and that they comply on their face with the requirements of such Letter of Credit and that any other drawing condition appearing on the face of such Letter of Credit has been satisfied in the manner so set forth.

  • Time Extensions 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).