Relief Event Defined. In this Agreement, “
Relief Event Defined. ‌ The occurrence of any of the following events during the Construction Phase shall constitute a Relief Event for which the Progressive Contractor shall be entitled to seek adjustments to the Baseline Pricing Package Schedule or the applicable Pricing Package GMP, as may be allowed under the Risk Register or otherwise pursuant to this Section 20 (Relief & Compensation) and Section 21 (Construction Phase Change Orders): (a) the occurrence of a Risk Register Event that is identified as a Department Risk; (b) the occurrence of a Provisional Risk Register Event with an uncapped Provisional Sum; (c) a Change in Law; (d) a Department-Caused Delay; (e) unavoidable delays arising from a suspension order pursuant to Section 23.1 (Suspension for Convenience);‌ (f) uncovering, removing, and restoring Work, to the extent additional costs or time are provided for in Section 11.4.1 (