Rectifying issues. 11.1 If there is a Notifiable Default, the Supplier must notify the Buyer within 3 Working Days of the Supplier becoming aware of the Notifiable Default and the Buyer may request that the Supplier provide a Rectification Plan within 10 Working Days of the Buyer’s request alongside any additional documentation that the Buyer requires. 11.2 When the Buyer receives a requested Rectification Plan it can either: 11.2.1 reject the Rectification Plan or revised Rectification Plan giving reasons; or 11.2.2 accept the Rectification Plan or revised Rectification Plan (without limiting its rights) in which case the Supplier must immediately start work on the actions in the Rectification Plan at its own cost. 11.3 Where the Rectification Plan or revised Rectification Plan is rejected, the Buyer: 11.3.1 will give reasonable grounds for its decision; and 11.3.2 may request that the Supplier provides a revised Rectification Plan within 5 Working Days.
Appears in 3 contracts
Sources: Contract, Contract for Services, Local Authority Childcare Sufficiency Support Contract
Rectifying issues. 11.1 12.1 If there is a Notifiable Default, the Supplier must notify the Buyer within 3 Working Days of the Supplier becoming aware of the Notifiable Default and the Buyer may request (whether notified or not) that the Supplier provide a Rectification Plan within 10 Working Days of the Buyer’s request alongside any additional documentation that the Buyer requires.
11.2 12.2 When the Buyer receives a requested Rectification Plan it can either:
11.2.1 12.2.1 reject the Rectification Plan or revised Rectification Plan Plan, giving reasons; or
11.2.2 12.2.2 accept the Rectification Plan or revised Rectification Plan (without limiting its rights) in which case the Supplier must immediately start work on the actions in the Rectification Plan at its own cost.
11.3 12.3 Where the Rectification Plan or revised Rectification Plan is rejected, the Buyer:
11.3.1 12.3.1 will give reasonable grounds for its decision; and
11.3.2 12.3.2 may request that the Supplier provides a revised Rectification Plan within 5 Working Days.
Appears in 2 contracts
Sources: Framework Contract, Network Rail Contract for Goods and/or Non Construction Services
Rectifying issues. 11.1 If there is a Notifiable Default, the Supplier must notify the Buyer within 3 three (3) Working Days of the Supplier becoming aware of the Notifiable Default and the Buyer may request that the Supplier provide a Rectification Plan within 10 ten (10) Working Days of the Buyer’s request alongside any additional documentation that the Buyer requires.
11.2 When the Buyer receives a requested Rectification Plan it can either:
11.2.1 reject the Rectification Plan or revised Rectification Plan giving reasons; or
11.2.2 accept the Rectification Plan or revised Rectification Plan (without limiting its rights) in which case the Supplier must immediately start work on the actions in the Rectification Plan at its own cost.
11.3 Where the Rectification Plan or revised Rectification Plan is rejected, the Buyer:
11.3.1 will give reasonable grounds for its decision; and
11.3.2 may request that the Supplier provides a revised Rectification Plan within 5 five (5) Working Days.
Appears in 2 contracts
Sources: Award Form, Contract for the Provision of Strategic Intelligence, Surveillance & Reconnaissance (Isr) Special Missions Aircraft Managed Service
Rectifying issues. 11.1 12.1 If there is a Notifiable Default, the Supplier must notify the Buyer within 3 three Working Days of the Supplier becoming aware of the Notifiable Default and the Buyer may request (whether notified or not) that the Supplier provide a Rectification Plan within 10 ten Working Days of the Buyer’s request alongside any additional documentation that the Buyer requires.
11.2 12.2 When the Buyer receives a requested Rectification Plan it can either:
11.2.1 12.2.1 reject the Rectification Plan or revised Rectification Plan Plan, giving reasons; or
11.2.2 12.2.2 accept the Rectification Plan or revised Rectification Plan (without limiting its rights) in which case the Supplier must immediately start work on the actions in the Rectification Plan at its own cost.
11.3 12.3 Where the Rectification Plan or revised Rectification Plan is rejected, the Buyer:
11.3.1 12.3.1 will give reasonable grounds for its decision; and
11.3.2 12.3.2 may request that the Supplier provides a revised Rectification Plan within 5 five Working Days.
Appears in 2 contracts
Sources: Framework Contract for Goods and/or Non Construction Services, Network Rail Contract for Goods and/or Non Construction Services
Rectifying issues. 11.1 12.1 If there is a Notifiable Default, the Supplier must notify the Buyer within 3 Working Days of the Supplier becoming aware of the Notifiable Default and the Buyer may request (whether notified or not) that the Supplier provide a Rectification Plan within 10 Working Days of the Buyer’s request alongside any additional documentation that the Buyer requiresDays.
11.2 12.2 When the Buyer receives a requested Rectification Plan it can either:
11.2.1 12.2.1 reject the Rectification Plan or revised Rectification Plan Plan, giving reasons; or
11.2.2 12.2.2 accept the Rectification Plan or revised Rectification Plan (without limiting its rights) in which case the Supplier must immediately start work on the actions in the Rectification Plan at its own cost, unless agreed otherwise by the Parties.
11.3 12.3 Where the Rectification Plan or revised Rectification Plan is rejected, the Buyer:
11.3.1 12.3.1 will give reasonable grounds for its decision; and
11.3.2 12.3.2 may request that the Supplier provides a revised Rectification Plan within 5 Working Days.
Appears in 2 contracts
Sources: Framework Contract for Goods and/or Non Construction Services, Network Rail Contract for Goods and/or Non Construction Services
Rectifying issues. 11.1 If there is a Notifiable Default, the Supplier must notify the Buyer within 3 three (3) Working Days of the Supplier becoming aware of the Notifiable Default De- fault and the Buyer may request that the Supplier provide a Rectification Plan within 10 ten (10) Working Days of the Buyer’s request alongside any additional documentation that the Buyer requires.
11.2 When the Buyer receives a requested Rectification Plan it can either:
11.2.1 reject the Rectification Plan or revised Rectification Plan giving reasonsrea- sons; or
11.2.2 accept the Rectification Plan or revised Rectification Plan (without limiting its rights) in which case the Supplier must immediately start work on the actions in the Rectification Plan at its own cost.
11.3 Where the Rectification Plan or revised Rectification Plan is rejected, the Buyer:
11.3.1 will give reasonable grounds for its decision; and
11.3.2 may request that the Supplier provides a revised Rectification Plan within 5 five (5) Working Days.
Appears in 1 contract
Sources: Award Form