Common use of Recovery Plan Clause in Contracts

Recovery Plan. Immediately upon learning of any event that may lead to a delay in the progress of the Scope of Services, A-E shall prepare a plan for recovery to the original Project Design Schedule, including any associated costs, impacts or related effects thereof. Upon receipt of such plan, COUNTY may direct A-E to execute the plan described, or a modification thereof.

Appears in 10 contracts

Samples: John Wayne Airport Agreement, John Wayne Airport Agreement, Airport Agreement

AutoNDA by SimpleDocs

Recovery Plan. Immediately upon learning of any event that may lead to a delay in the progress of the Scope of Services, A-E shall prepare a plan for recovery to the original Project Design Schedule, including any associated costs, impacts or related effects thereof. Upon receipt of such plan, COUNTY may direct A-E to execute the plan described, or a modification thereof.

Appears in 5 contracts

Samples: cams.ocgov.com, cams.ocgov.com, Agreement

AutoNDA by SimpleDocs