Common use of Re-Study Clause in Contracts

Re-Study. If Re-Study of the Interconnection System Impact Study is required due to a higher queued project dropping out of the queue, or a modification of a higher queued project subject to Section 4.4, or re-designation of the Point of Interconnection pursuant to Section 7.2 Transmission Provider shall notify Interconnection Customer in writing. Such Re-Study shall take no longer than sixty (60) Calendar Days from the date of notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.

Appears in 9 contracts

Samples: Study Agreement, Study Agreement, Study Agreement

AutoNDA by SimpleDocs

Re-Study. If Re-Study of the Interconnection System Impact Study is required due to a higher queued project dropping out of the queue, or a modification of a higher queued project subject to Section 4.4, or re-designation of the Point of Interconnection pursuant to Section 7.2 7.2, Transmission Provider shall notify Interconnection Customer in writing. Such Transmission Provider shall use Reasonable Efforts to complete such Re-Study shall take no longer than within sixty (60) Calendar Days from the date of notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.

Appears in 5 contracts

Samples: Study Agreement, Agreement, Study Agreement

Re-Study. If Rere-Study study of the Interconnection System Impact Study is required due to a higher queued project dropping out of withdrawing from the queue, or a modification of a higher queued project subject to Section 4.4, or re-designation of the Point of Interconnection pursuant to Section 7.2 7.2, Transmission Provider shall notify Interconnection Customer in writing. Such Rere-Study study shall take no longer than sixty (60) Calendar Days from the date of notice. Any In accordance with Section 7.1, Interconnection Customer shall pay the estimated cost of Re-Study shall be borne by the Interconnection Customer being re-studiedstudy in advance and shall pay for the actual cost of the re-study.

Appears in 4 contracts

Samples: Generator Interconnection Agreement, Confidentiality Agreement, Generator Interconnection Agreement

Re-Study. If Re-Study of the Interconnection System Impact Study is required due to a higher queued project dropping out of the queue, or a modification of a higher queued project subject to Section 4.4, or re-designation of the Point of Interconnection pursuant to Section 7.2 . Transmission Provider shall so notify Interconnection Customer in writing. Such Transmission Provider shall use Reasonable Efforts to complete the Re-Study shall take no longer than sixty within ninety (6090) Calendar Days from the date of notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studiedCustomer.

Appears in 3 contracts

Samples: Study Agreement, Study Agreement, Study Agreement

Re-Study. If Re-Study of the Interconnection System Impact Study is required due to a higher queued project dropping out of the queue, or a modification of a higher queued project subject to Section 4.4, or re-designation of the Point of Interconnection pursuant to Section 7.2 Transmission Provider shall notify Interconnection Customer in writing. Such Re-Study shall take no longer than sixty (60) Calendar Days from the date of notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.

Appears in 2 contracts

Samples: Study Agreement, Study Agreement

Re-Study. If Re-Study of the Serial Interconnection System Impact Study is required due to a higher queued project dropping out of the queue, or a modification of a higher queued project subject to Section 4.45.4, or re-designation of the Point of Interconnection pursuant to Section 7.2 9.2, Transmission Provider shall notify Interconnection Customer in writing. Such Re-Study shall take no longer than sixty (60) Calendar Days from the date of notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.

Appears in 1 contract

Samples: Agreement

AutoNDA by SimpleDocs

Re-Study. If Re-Study of the Serial Interconnection System Impact Study is required due to a higher queued project dropping out of the queue, or a modification of a higher queued project subject to Section 4.45.4, or re-designation of the Point of Interconnection pursuant to Section 7.2 9.2, Transmission Provider shall notify Interconnection Customer in writing. Such Re-Study shall take no longer than sixty (60) Calendar Days from the date of notice. Any cost of Re-Re- Study shall be borne by the Interconnection Customer being re-studied.

Appears in 1 contract

Samples: Agreement

Re-Study. If Re-Study of the Serial Interconnection System Impact Study is required due to a higher queued project dropping out of the queue, or a modification of a higher queued project subject to Section 4.445.4, or re-designation of the Point of Interconnection pursuant to Section 7.2 79.2 Transmission Provider shall notify Interconnection Customer in writing. Such Re-Study shall take no longer than sixty (60) Calendar Days from the date of notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Re-Study. If Re-Study of the Interconnection System Impact Study is required due to a higher queued project dropping out of the queue, or a modification of a higher queued project subject to Section 4.4, or re-re- designation of the Point of Interconnection pursuant to Section 7.2 6.1 Transmission Provider shall notify Interconnection Customer in writing. Such Re-Study shall take no longer than sixty (60) Calendar Days from the date of notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.

Appears in 1 contract

Samples: Study Agreement