Punch List Completion. 10.1. The Contractor understands and agrees that time is of the essence in closing out the Work of this Contract. Upon Substantial Completion of the Work, the Punch List will be transmitted to the Contractor from the Sourcewell Member. The Contractor agrees to begin performance of Punch List Work immediately after receipt of the Punch List. 10.2. Failure of the Contractor or its Subcontractors to begin the Punch List Work within three (3) business days after receipt of the Punch List will be construed as failure to prosecute the Work of the Contract. 10.3. Punch List Work will be continuously prosecuted once begun and completed within 30 Days from the receipt of the Punch List. Should the Contractor fail to complete the Punch List within this period of time, the liquidated damages as identified in Article 26 of the Contract General Conditions will apply.
Appears in 1 contract
Sources: Construction Services Agreement
Punch List Completion.
10.1. The Contractor understands and agrees that time is of the essence in closing out the Work of this Contract. Upon Substantial Completion of the Work, the Punch List will be transmitted to the Contractor from the Sourcewell NJPA Member. The Contractor agrees to begin performance of Punch List Work immediately after receipt of the Punch List.
10.2. Failure of the Contractor or its Subcontractors to begin the Punch List Work within three (3) business days after receipt of the Punch List will be construed as failure to prosecute the Work of the Contract.
10.3. Punch List Work will be continuously prosecuted once begun and completed within 30 thirty (30) Days from the receipt of the Punch List. Should the Contractor fail to complete the Punch List within this period of time, the liquidated damages as identified in Article 26 30 of the Contract General Conditions will apply.
Appears in 1 contract