Punch List Completion. The Contractor understands and agrees that time is of the essence in closing out the Work of this Contract. Upon Substantial Completion of the Work, the Punch List will be transmitted to the Contractor from the Member. The Contractor agrees to begin performance of Punch List Work immediately after receipt of the Punch List. Failure of the Contractor or its Subcontractors to begin the Punch List Work within three (3) business days after receipt of the Punch List will be construed as failure to prosecute the Work of the Contract. Punch List Work will be continuously prosecuted once begun and completed within thirty (30) Days from the receipt of the Punch List. Should the Contractor fail to complete the Punch List within this period of time, the liquidated damages (See Section Three: General Terms and Conditions for JOC, Article 45, Liquidated Damages) Contract General Conditions will apply.
Appears in 6 contracts
Sources: Master Agreement, Master Agreement, Master Agreement