Common use of Project Suspension Clause in Contracts

Project Suspension. If the District suspends the Project for more than one hundred twenty (120) consecutive days, Architect shall be compensated for Services performed prior to notice of that suspension. When the Project is resumed, the schedule shall be adjusted and Architect’s compensation shall be equitably adjusted to provide for expenses incurred in the resumption of the Architect’s Services. Architect shall make every effort to maintain the same Project personnel after suspension. If the District suspends the Project for more than two (2) years, Architect may terminate this Agreement by giving written notice.

Appears in 12 contracts

Sources: Architectural Services Agreement, Architectural Services Agreement, Architectural Services Agreement

Project Suspension. If the District suspends the Project for more than one hundred twenty (120) consecutive days, Architect shall be compensated for Services performed prior to notice of that suspension. When the Project is resumed, the schedule shall be adjusted and Architect’s compensation shall be equitably adjusted to provide for expenses incurred in the resumption of the Architect’s Services. Architect shall make every effort to maintain the same Project personnel after suspension. If the District suspends the Project for more than two (2) years, Architect may terminate this Agreement by giving written notice.

Appears in 2 contracts

Sources: Architectural Services Agreement, Architectural Services Agreement

Project Suspension. If the District suspends the a Project for more than one hundred twenty (120) consecutive days, Architect shall be compensated for Services performed prior to notice of that suspension. When the that Project is resumed, the schedule shall be adjusted and Architect’s compensation shall be equitably adjusted to provide for expenses incurred in the resumption of the Architect’s Services. Architect shall make every effort to maintain the same Project personnel after suspension. If the District suspends the that Project for more than two (2) years, Architect may terminate this Agreement by giving written notice.

Appears in 1 contract

Sources: Master Agreement for Architectural Services

Project Suspension. If the District suspends the a Project for more than one hundred twenty (120) consecutive calendar days, Architect shall be compensated for Services performed prior to notice of that suspension. When the a Project is resumed, the schedule shall be adjusted and Architect’s compensation shall be equitably adjusted to provide for expenses incurred in the resumption of the Architect’s Services. Architect shall make every effort to maintain the same Project personnel after suspension. If the District suspends the a Project for more than two (2) years, Architect may terminate this Agreement by giving written notice.

Appears in 1 contract

Sources: Master Agreement for Architectural Services

Project Suspension. If the District suspends the a Project for more than one hundred twenty (120) consecutive days, Architect shall be compensated for Services performed prior to notice of that suspension. When the Project is resumed, the schedule shall be adjusted and Architect’s compensation shall be equitably adjusted to provide for expenses incurred in the resumption of the Architect’s Services. Architect shall make every effort to maintain the same Project personnel after suspension. If the District suspends the a Project for more than two (2) years, Architect may terminate this Agreement by giving written notice.

Appears in 1 contract

Sources: Master Agreement for Architectural Services