Project Grogram Sample Clauses
Project Grogram. 4.1.1 The determining principle of critical path and critical path change in project schedule: not affect the construction period and agreed in writing by the Employer. On the condition that the Employer fails to complete the approval within 3 working days and to raise any objection after receiving the document, it is deemed that the Employer have accepted the critical path and the critical path change in the project program.
4.1.2 Copies and time of project program submitted by the Contractor: before the 5th day of each month, six copies of the monthly project schedule (including two copies for the supervisor and four copies for the employer) shall be submitted.