Procurement Plan. JP Autoceste FBiH has prepared a procurement plan. The estimated values are planned, but real values will be determined after completion of the main project and tender procedures. Please consider that contracted values are given in detail under Chapter 10. 1. MOTORWAY CONSTRUCTION a) Klopče – Donja Gračanica 110.000 OPEC 107.879 Construction works Open Oct-14 May-16 Nov-181 2. SUPERVISION a) Klopče - Donja Gračanica 3.000 OPEC 5.473 Supervision Competitive Oct-14 May-16 Nov-20 3. EXPROPRIATION 6.840 JPAFBiH 4. VAT 17% 19.210 JPAFBiH 5. TOTAL 26.050 JPAFBiH 6. TOTAL 60.000 OPEC 1 Addendum 1 - Deadline for completion of construction works has been extended until November, 2019
Appears in 1 contract
Sources: Loan Agreement
Procurement Plan. JP Autoceste FBiH has prepared a procurement plan. The estimated values are planned, but real values will be determined after completion of the main project and tender procedures. Please consider that contracted values are given in detail under Chapter 10. 1. MOTORWAY CONSTRUCTION a) Klopče – Donja Gračanica 110.000 36.000 OPEC EBRD 107.879 Construction works Open Oct-14 May-16 Nov-181 Nov-191 2. SUPERVISION SUPERVISION
a) Klopče - Donja Gračanica 3.000 OPEC 5.473 Supervision Competitive Oct-14 May-16 Nov-20 3. EXPROPRIATION 6.840 7.138 JPAFBiH 4. VAT 17% 19.210 25.330 JPAFBiH 5. TOTAL 26.050 32.468 JPAFBiH 6. TOTAL 60.000 149.000 OPEC EBRD 1 Addendum 1 2 - Deadline for completion of construction works has been extended until November, 2019.
Appears in 1 contract
Sources: Loan Agreement
Procurement Plan. JP Autoceste FBiH has prepared a procurement plan. The estimated values are planned, but real values will be determined after completion of the main project and tender procedures. Please consider that contracted values are given in detail under Chapter 10. 1. MOTORWAY CONSTRUCTION a) Klopče – Donja Gračanica 110.000 36.000 OPEC EBRD 107.879 Construction works Open Oct-14 May-16 Nov-181 Nov-191 2. SUPERVISION SUPERVISION
a) Klopče - Donja Gračanica 3.000 OPEC 5.473 Supervision Competitive Oct-14 May-16 Nov-20 3. EXPROPRIATION 6.840 7.129 JPAFBiH 4. VAT 17% 19.210 25.330 JPAFBiH 5. TOTAL 26.050 32.459 JPAFBiH 6. TOTAL 60.000 96.000 OPEC EBRD 1 Addendum 1 - Deadline for completion of construction works has been extended until November, 2019
Appears in 1 contract
Sources: Loan Agreement