Process for Development; Contractor’s Response Sample Clauses

Process for Development; Contractor’s Response. No later than twenty (20) calendar days after delivering the notice of substantial completion, the City will deliver to the Contractor a punch list and related questions. The punch list must identify the remaining items required to render the construction services complete, satisfactory, and acceptable to the City and for the Contract to meet its obligations under this Contract. The Contractor must deliver a response to all questions no later than five (5) calendar days after receipt. The City will deliver the final punch list no later than five (5) calendar days after receiving the Contractor’s response.