Common use of Pre-Resolution Procedure Clause in Contracts

Pre-Resolution Procedure. A Contractor raising an issue related to a breach of contract or an issue concerning time or money shall file a Pre Resolution request to County Project Manager as a prerequisite for any consideration of the issue by the County. . 42.1.1 The Pre-Resolution request must be filed in writing by Contractor with the County Project Manager within twenty-one (21) days of issuance of the occurrence in which Contractor disagrees with such assessment or an issuance of a denial of a written request by Contractor for additional monies or time. 42.1.2 County shall issue to Contractor a written decision providing the basis for the decision of the issues presented by all of the parties within thirty (30) days of receipt of all of the information required by County in Section 18.0.

Appears in 2 contracts

Sources: Construction Agreement, Construction Agreement

Pre-Resolution Procedure. A Contractor raising an issue related to a breach of contract or an issue concerning time or money shall file a Pre Resolution request to County Project Manager as a prerequisite for any consideration of the issue by the County. . 42.1.1 The Pre-Resolution request must be filed in writing by Contractor with the County Project Manager within twenty-one (21) days of issuance of the occurrence in which Contractor disagrees with such assessment or an issuance of a denial of a written request by Contractor for additional monies or time. 42.1.2 County shall issue to Contractor a written decision providing the basis for the decision of the issues presented by all of the parties within thirty (30) days of receipt of all of the information required by County in Section 18.0.

Appears in 1 contract

Sources: Construction Agreement