Phase Two Cluster Study Sample Clauses

Phase Two Cluster Study. At the completion of the final Phase One Cluster Study Customer Review Period following the Phase One Cluster Study process, Interconnection Customers that timely submitted a valid Phase Two Cluster Study Agreement, in the form of Appendix 4 of this Attachment R, Phase Two Cluster Study deposit, and validated detailed modeling data shall proceed to the Phase Two Cluster Study. Transmission Provider shall conduct a Phase Two Cluster Study in accordance with Section 7 of the LGIP, except that Section 7.5.1 shall not apply. Commercial Readiness Milestone Options applicable to the Phase Two Customer Review Period pursuant to this Attachment R are set forth below in Section 3.3.1.
Phase Two Cluster Study