Phase II - Final Design Clause Samples
Phase II - Final Design. 2.3.1 The Engineer shall submit to the Director within ten days of any Notice to Proceed for Phase II, the Project Schedule updated to reflect firm dates for the beginning and end of each activity set forth therein and the review dates for such activities.
2.3.2 The Engineer shall submit a detailed construction cost estimate at the 60%, 90%, and Bid Ready Drawings stages:
2.3.2.1 Engineer shall inform the Director of any adjustments to previous estimates of the Project construction cost which are indicated by market conditions or authorized changes in the scope and requirements of the Project within five business days of determining the adjustment; and
2.3.2.2 Engineer does not guarantee that bids will not vary from the final construction cost estimate.
2.3.3 The Engineer shall submit «ph2copy» copies of the recommendations, analyses and other deliverables identified in this Contract in hard copy format and one electronic copy in the format requested by the Director.
Phase II - Final Design. Based upon approved preliminary design Documents and any further adjustments in the scope or quality of the Project authorized by the Director, Phase II services include, but are not limited to, the following:
3.1.2.3.2.1. Submit the Project Schedule updated to reflect firm dates for the beginning and end of each activity and the review dates within 10 days of receiving the Letter of Authorization with Phase II.
3.1.2.3.2.2. Prepare detailed Construction Documents based on guidelines provided by the Director. The Construction Documents must list recommended alternate bid items for the Project in a manner that permits ready evaluation and comparison. Specifications must conform to City of Houston and other regulatory agency standards.
3.1.2.3.2.3. Inform the Director of any adjustments to previous estimates of the Project Construction Cost which are indicated by market conditions or authorized changes in the scope and requirements of the Project. The Engineer does not guarantee that bids will not vary from the estimate.
3.1.2.3.2.4. Prepare and submit the required Documents to obtain approval of all governmental authorities having jurisdiction over the design or operation of the Project and all public and private utilities, including pipeline transmission and railroad companies affected by the Project; obtain the signatures of representatives of these governmental authorities and public and private utilities; obtain the signatures of City officials indicated by the City’s standard title block for drawings.
3.1.2.3.2.5. Design the Project in compliance with the requirements of applicable laws, codes, and regulations, including the City of Houston Building Code and FAA and TSA directives, rules, and regulations; make revisions to the Contract Documents necessary to provide clarifications or to correct discrepancies; and provide the Director with Documents necessary for obtaining a City building permit and other required permits for the Project. The Construction Documents must conform to applicable federal, state, and City regulations.
3.1.2.3.2.6. Deliver to the Director:
3.1.2.3.2.6.1. a detailed cost estimate at the 65%, 95%, and 100% overall completion stages which occur during Phase II;
3.1.2.3.2.6.2. eight copies identified in
3.1.2.3.2.7. Assist the City in securing bids for the construction of the Project based on the Construction Documents; attend pre-bid conferences; assist the City in evaluating the bid proposals; prepare tabulations of bids receive...
Phase II - Final Design. 2.3.1 The engineering and design plans shall be developed in accordance with the latest edition and revisions of the State’s Highway Design Division Operations and Procedures Manual or the American Association of State Highway and Transportation Official’s A Policy on Geometric Design of Highways and Streets, the Department of Transportation’s 1993 Standard Specifications for Construction of Highways, Streets and Bridges, federal regulations for conformity with the Clean Air Act air quality requirements, the EPA-National Pollutant Discharge Elimination System requirements, the Texas Accessibility Standards of the Architectural Barriers Act, and the Texas Manual on Uniform Traffic Control Devices, hereinafter collectively referred to as ”TxDOT Specifications”.
Phase II - Final Design. 1.1.1 The Engineer shall provide overlay and curb ramps quantities and cost estimates. The Engineer shall develop graphic curb ramp layout design sketches over photographs and a graphical limit of the overlay.
1.1.2 The Engineer shall provide the City with all applicable pavement rehabilitation and construction options
Phase II - Final Design. Based upon approved preliminary design Documents and any further adjustments in the scope or quality of the Project authorized by the Director, Phase II services include, but are not limited to, the following:
3.1.2.3.2.1 Submit the Project Schedule updated to reflect firm dates for the beginning and end of each activity and the review dates within 10 days of receiving the Notice to Proceed with Phase II.
3.1.2.3.2.2 Prepare detailed Construction Documents based on guidelines provided by the Director. The Construction Documents must list recommended alternate bid items for the Project in a manner that permits ready evaluation and comparison. Specifications must conform to City of Houston and other regulatory agency standards.
3.1.2.3.2.3 Inform the Director of any adjustments to previous estimates of the Project Construction Cost which are indicated by market conditions or authorized changes in the scope and requirements of the Project. The Engineer does not guarantee that bids will not vary from the estimate.