Common use of Package or Request Clause in Contracts

Package or Request. The Parties agree that in the event that the Work is not provided by this 2 date, actual damages to ANAHEIM as a result of that failure would be impractical or extremely 3 difficult to ascertain. In the event of CONTRACTOR’s failure to complete the Work by the 4 date specified in the Work Order Package or Request, CONTRACTOR agrees to pay 5 ANAHEIM liquidated damages for every calendar day’s delay beyond the completion date 6 specified in the Work Order Package or Request an amount equal to either (a) Five Hundred 7 Dollars ($500.00) per calendar day; or (b) the liquidated damages amount, if any, specified in an 8 applicable Work Order Package or Request. The foregoing sentence shall be subject to Part

Appears in 2 contracts

Sources: Master Construction Agreement, Master Construction Agreement