Nonbinding Mediation. (a) Any disputed portion of the Claim, as identified by the contractor in writing, shall be submitted to nonbinding mediation, with the Agency and the Contractor sharing the associated costs equally. The Agency and Contractor shall mutually agree to a mediator within ten (10) business days after the disputed portion of the Claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the Claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. (b) Mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this Article. (c) If mediation is unsuccessful, the parts of the Claim remaining in dispute shall be subject to applicable procedures outside this Article. (d) Unless otherwise agreed to by the Agency and the Contractor in writing, the mediation conducted pursuant to this Article shall excuse any further obligation under Section 20104.4 of the Public Contract Code to mediate after litigation has been commenced. (e) The Claim resolution procedures in this Article do not preclude the Agency from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program, if mediation under this Article does not resolve the parties’ dispute.
Appears in 1 contract
Sources: Construction Contract
Nonbinding Mediation. (a) Any disputed portion of the Claim, as identified by the contractor in writing, shall be submitted to nonbinding mediation, with the Agency AGENCY and the Contractor CONTRACTOR sharing the associated costs equally. The Agency AGENCY and Contractor CONTRACTOR shall mutually agree to a mediator within ten (10) business days after the disputed portion of the Claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the Claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator.
(b) Mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this Article.
(c) If mediation is unsuccessful, the parts of the Claim remaining in dispute shall be subject to applicable procedures outside this Article.
(d) Unless otherwise agreed to by the Agency AGENCY and the Contractor CONTRACTOR in writing, the mediation conducted pursuant to this Article shall excuse any further obligation under Section 20104.4 of the Public Contract Code to mediate after litigation has been commenced.
(e) The Claim resolution procedures in this Article do not preclude the Agency from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program, if mediation under this Article does not resolve the parties’ dispute.
Appears in 1 contract
Sources: Contract