Common use of MTA Right to Update the Master Program Schedule Clause in Contracts

MTA Right to Update the Master Program Schedule. If the SI does not timely submit an MPS Update or the Engineer determines that a submitted MPS Update is inadequate, then the MTA may, in its sole discretion and for its own internal use, update the Master Program Schedule with its own personnel (and personnel of other MTA Group entities) or by engaging Third Parties (each, an "MTA-Prepared MPS Update"). The SI shall be solely responsible for all costs incurred by the MTA in preparing an MTA-Prepared MPS Update. The preparation of an MTA-Prepared MPS Update shall not relieve the SI's obligation to prepare and submit all required MPS Updates as required pursuant to the Contract Documents, including those that trigger the preparation of MTA-Prepared MPS Updates.

Appears in 2 contracts

Sources: New Fare Payment System Contract, New Fare Payment System Contract