Modification Costs. Developer shall not be assigned the costs of any additions, modifications, or replacements that Connecting Transmission OwnerAffected System Operator makes to the Connecting Transmission Owner’s AttachmentAffected System Upgrade Facilities or the New York State Transmission System to facilitate the interconnection of a third party to the Connecting Transmission Owner’s AttachmentAffected System Upgrade Facilities or the New York State Transmission System, or to provide Transmission Service to a third party under the ISO OATT, except in accordance with the cost allocation procedures in Attachment S of the ISO OATT. Developer shall be responsible for the costs of any additions, modifications, or replacements to the Developer’s Attachment Facilities that may be necessary to maintain or upgrade such Developer’s Attachment Facilities consistent with Applicable Laws and Regulations, Applicable Reliability Standards or Good Utility Practice.
Appears in 9 contracts
Sources: Standard Large Generator Interconnection Service Agreement, Engineering, Procurement, and Construction Agreement, Engineering, Procurement, and Construction Agreement
Modification Costs. Transmission Developer or Connecting Transmission Owner, as applicable, shall not be assigned the costs of any additions, modifications, or replacements that Connecting Transmission OwnerAffected System Operator Ownerthe other Party makes to the Connecting Transmission Owner’s AttachmentAffected System Upgrade Attachment Facilities or the New York State Transmission System to facilitate the interconnection of a third party to the Connecting Transmission Owner’s AttachmentAffected System Upgrade Attachment Facilities or the New York State Transmission System, or to provide Transmission Service to a third party under the ISO OATT, except in accordance with the cost allocation procedures in Attachment S of the ISO OATT. Developer shall be responsible for the costs of any additions, modifications, or replacements to the Developer’s Attachment Facilities that may be necessary to maintain or upgrade such Developer’s Attachment Facilities consistent with Applicable Laws and Regulations, Applicable Reliability Standards or Good Utility Practice.
Appears in 6 contracts
Sources: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement
Modification Costs. Developer DeveloperInterconnection Customer shall not be assigned the costs of any additions, modifications, or replacements that Connecting Transmission OwnerAffected System Operator makes to the Connecting Transmission Owner’s AttachmentAffected System Upgrade Facilities or the New York State Transmission System to facilitate the interconnection of a third party to the Connecting Transmission Owner’s AttachmentAffected System Upgrade Facilities or the New York State Transmission System, or to provide Transmission Service to a third party under the ISO OATT, except in accordance with the cost allocation procedures in Attachment S of the ISO OATT. Developer shall be responsible for the costs of any additions, modifications, or replacements to the Developer’s Attachment Facilities that may be necessary to maintain or upgrade such Developer’s Attachment Facilities consistent with Applicable Laws and Regulations, Applicable Reliability Standards or Good Utility Practice.
Appears in 2 contracts
Sources: Interconnection Service Agreement, Engineering, Procurement, and Construction Agreement
Modification Costs. Transmission Developer or Affected System Operator, as applicable, shall not be assigned the costs costscost of any additions, modifications, or replacements that Connecting Transmission OwnerAffected System Operator Ownerthe other Party makes to the Connecting Transmission Owner’s AttachmentAffected System Upgrade Attachment Facilities or the New York State Transmission System to facilitate the interconnection of a third party to the Connecting Transmission Owner’s AttachmentAffected System Upgrade Attachment Facilities or the New York State Transmission System, or to provide Transmission Service to a third party under the ISO OATT, except in accordance with the cost allocation procedures in Attachment S of the ISO OATT. Developer shall be responsible for the costs of any additions, modifications, or replacements to the Developer’s Attachment Facilities that may be necessary to maintain or upgrade such Developer’s Attachment Facilities consistent with Applicable Laws and Regulations, Applicable Reliability Standards or Good Utility Practice.
Appears in 2 contracts
Sources: Standard Large Generator Interconnection Agreement, Interconnection Agreement