Maximum Allowable Extension. Notwithstanding anything in this Agreement to the contrary, the Initial Delivery Deadline may not be later than the first day of the month occurring forty-eight (48) months after CPUC Approval (the “Guaranteed Delivery Deadline”). In no event may Seller extend the Initial Delivery Deadline beyond the Guaranteed Delivery Deadline as a result of the failure to obtain Permits, due to interconnection delay, Force Majeure, or by payment of Daily Delay Liquidated Damages, or any combination thereof.
Appears in 4 contracts
Sources: Renewable Power Purchase Agreement, Renewable Power Purchase Agreement, Renewable Power Purchase Agreement