Common use of Look-Ahead Schedule Clause in Contracts

Look-Ahead Schedule. ‌ 10 The Look-Ahead Schedule is a computer-generated bar chart that indicates the previous week’s 11 Work and the Work planned for the next 3 weeks. Developer shall base the Look-Ahead 12 Schedule on the Project Schedule, and provide a greater breakdown of the Project Schedule 13 activities for the purpose of materials inspection and testing. The Look-Ahead Schedule must 14 clearly note and explain any Deviations from the Project Schedule. Developer shall reference 15 the Project Schedule activity identification numbers and define subsequent specific daily 16 operations for all Work activities scheduled to be performed during the 4-week period. At least 1 17 day prior to the weekly Project meeting, Developer shall submit weekly Look-Ahead Schedules 18 to ADOT.

Appears in 3 contracts

Sources: Design Build Maintain Agreement, Design Build Maintain Agreement, Design Build Maintain Agreement