Liaison and Progress Reports Sample Clauses
Liaison and Progress Reports. 6.2.1. There shall be continuous liaison between the representatives of the Parties throughout the period from the execution of this Agreement until the Operational Date.
6.2.2. There shall be meetings between the Parties at least every month, or at any other period agreed by the Parties, and each Party shall provide to the other progress reports on a monthly basis detailing that Party's progress towards constructing and providing the works for the connection and meeting its obligations. The first such report shall be submitted within five (5) Business Days of expiry of the first month following execution of this Agreement and further reports within five (5) Business Days of expiry of each subsequent quarter.
6.2.3. The progress reports shall cover in reasonable detail the relevant aspects of progress towards obtaining the relevant Consents, design, construction, commissioning and testing of the Connection Works and shall highlight actual or potential departures from the Construction Programme. Where necessary, the progress reports shall state the proposed measures to be taken by NEPCO or the “User” to overcome any departures from programme.
6.2.4. When a delay to any of the key dates in the Construction Programme is inevitable, the delayed Party shall advise the other Party of the delay and shall produce a revised Construction Programme for review.
Liaison and Progress Reports a) There shall be quarterly meetings between the User and STU, and each Party shall provide to the other progress reports and their respective progress towards the connection works and other works associated with the Inter- connection point as the case may be, in order to meet their respective obligations.
b) The progress reports shall cover in reasonable detail, the relevant aspects of progress towards obtaining the relevant Consents, design, construction, commissioning and testing of the Connection Works and works associated with connection works.