Common use of INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES Clause in Contracts

INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 C The Contractor shall complete the required work of installing, maintaining and removing the traffic control devices for lane closures and restoring traffic to the existing traffic pattern. The Contractor shall not close or narrow two lanes of traffic on I-40/I-85 during the following time restrictions: DAY AND TIME RESTRICTIONS Monday thru Sunday From 6:00 a.m. to 10:00 p.m. The time of availability for this intermediate contract time will be the time the Contractor begins to install traffic control devices required for the lane closures according to the time restrictions stated herein. The completion time for this intermediate contract time will be the time the Contractor is required to complete the removal of traffic control devices required for the lane closures according to the time restrictions stated herein and restore traffic to the existing traffic pattern. The liquidated damages are Two Thousand Dollars ($ 2,000.00) per fifteen (15) minute time period.

Appears in 2 contracts

Samples: Proposal Item Sheet, Proposal Item Sheet

AutoNDA by SimpleDocs

INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 C D The Contractor shall complete the required work of installing, maintaining and removing the traffic control devices for lane road closures and restoring traffic to the existing traffic pattern. The Contractor shall not close any Ramp or narrow two lanes of traffic on I-40/I-85 Loop at the NC 33 or NC 4 interchanges during the following time restrictions: DAY AND TIME RESTRICTIONS Monday thru Monday-Thursday 7:00AM-8:00PM Friday-Sunday From 6:00 a.m. to 10:00 p.m. 7:00AM-10:00PM The time of availability for this intermediate contract time will be the time the Contractor begins to install traffic control devices required for the lane road closures according to the time restrictions stated herein. The completion time for this intermediate contract time will be the time the Contractor is required to complete the removal of traffic control devices required for the lane road closures according to the time restrictions stated herein and restore traffic to the existing traffic pattern. pattern The liquidated damages are Two One Thousand Dollars ($ 2,000.00$1,000.00) per fifteen (15) minute time periodhour.

Appears in 1 contract

Samples: Proposal Item Sheet

INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 C The Contractor shall complete the required work of installing, maintaining and removing the traffic control devices for lane closures and restoring traffic to the existing traffic pattern. The Contractor shall not close or narrow two (2) lanes of traffic on I-40/I-85 I-40 during the following time restrictions: DAY AND TIME RESTRICTIONS Monday thru Sunday From Sunday, 6:00 a.m. to 10:00 p.m. The time of availability for this intermediate contract time will be the time the Contractor begins to install traffic control devices required for the lane closures according to the time restrictions stated herein. The completion time for this intermediate contract time will be the time the Contractor is required to complete the removal of traffic control devices required for the lane closures according to the time restrictions stated herein and restore traffic to the existing traffic pattern. The liquidated damages are Two One Thousand Eight Hundred Seventy Five Dollars ($ 2,000.001,875.00) per fifteen (15) minute time period.

Appears in 1 contract

Samples: Proposal Item Sheet

INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 C D The Contractor shall complete the required work of installing, maintaining and removing the traffic control devices for lane road closures and restoring traffic to the existing traffic pattern. The Contractor shall not close or narrow two lanes of traffic on I-40/I-85 I-95 CD, Ramps & Loops at US 264 during the following time restrictions: DAY AND TIME RESTRICTIONS Monday thru through Thursday, 5:00am to 11:00pm And Friday 5:00am to Sunday From 6:00 a.m. to 10:00 p.m. 12:00am (Midnight) The time of availability for this intermediate contract time will be the time the Contractor begins to install traffic control devices required for the lane road closures according to the time restrictions stated herein. The completion time for this intermediate contract time will be the time the Contractor is required to complete the removal of traffic control devices required for the lane road closures according to the time restrictions stated herein and restore traffic to the existing traffic pattern. pattern The liquidated damages are Two One Thousand Dollars ($ 2,000.00$1000.00) per fifteen (15) minute time periodhour.

Appears in 1 contract

Samples: Proposal Item Sheet

AutoNDA by SimpleDocs

INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 C A The Contractor shall complete the required work of installing, maintaining and removing the traffic control devices for lane closures and restoring traffic to the existing traffic pattern. The Contractor shall not close or narrow two lanes a lane of traffic on I-40/I-85 (two lanes) during the following time restrictions: DAY AND TIME RESTRICTIONS Monday thru Sunday From 6:00 a.m. A.M. to 10:00 p.m. P.M. The time of availability for this intermediate contract time will be the time the Contractor begins to install traffic control devices required for the lane closures according to the time restrictions stated herein. The completion time for this intermediate contract time will be the time the Contractor is required to complete the removal of traffic control devices required for the lane closures according to the time restrictions stated herein and restore traffic to the existing traffic pattern. The liquidated damages are Two Thousand Five Hundred Dollars ($ 2,000.002,500.00) per fifteen (15) minute time period.

Appears in 1 contract

Samples: connect.ncdot.gov

INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES. (2-20-07) 108 SP1 G14 C D The Contractor shall complete the required work of installing, maintaining and removing the traffic control devices for lane road closures and restoring traffic to the existing traffic pattern. The Contractor shall not close or narrow two lanes of traffic on I-40/I-85 I-95 during the following time restrictions: DAY AND TIME RESTRICTIONS Monday thru through Thursday from 6:00 A.M. to 9:00 P.M. and Friday 6:00 A.M. to Sunday From 6:00 a.m. to 10:00 p.m. 9:00 P.M. The time of availability for this intermediate contract time will be the time the Contractor begins to install traffic control devices required for the lane road closures according to the time restrictions stated herein. The completion time for this intermediate contract time will be the time the Contractor is required to complete the removal of traffic control devices required for the lane road closures according to the time restrictions stated herein and restore traffic to the existing traffic pattern. pattern The liquidated damages are Two Thousand Five Hundred Dollars ($ 2,000.00$2,500.00) per fifteen (15) 15 minute time period.

Appears in 1 contract

Samples: connect.ncdot.gov