Interference with Tests. If by reason of any failure of the Purchaser (except any failure caused by an event of Force Majeure) to comply with its obligations under Clause 11 to make available requisite the Purchaser Input including the feedstock as per the schedule in the Programme, or such date as mutually agreed between the Parties (except for events of Force Majeure), or if by reason of any act or omission of the Purchaser, the Engineer or some other contractor employed by the Purchaser, the Contractor shall be prevented from carrying out the Tests on Completion and achieve the requirements for the issuance of a Taking Over Certificate in accordance with Clause 29 then the date stipulated in the Contract for the Final Performance Acceptance, achievement of which has been prevented or delayed, shall be extended by the period of such delay which has affected each such Test, and the Contractor shall be entitled to request for an extension of Time for Completion under Clause 33 and additional Cost incurred by the Contractor under Clause 41.
Appears in 2 contracts
Sources: Engineering, Procurement, Construction and Commissioning Contract (Mission NewEnergy LTD), Engineering, Procurement, Construction and Commissioning Contract (Mission NewEnergy LTD)