Interconnection Facilities Studies Processing Time. (A) Number of Interconnection Requests that had Interconnection Facilities Studies that are completed within Transmission Provider’s coordinated region during the reporting quarter and tendered to the Interconnection Customer in draft form, (B) Number of Interconnection Requests that had Interconnection Facilities Studies that are completed within Transmission Provider’s coordinated region during the reporting quarter that were completed and tendered to the Interconnection Customer in draft form more than ninety (90) or one hundred eighty (180) Calendar Days, as appropriate for that study, after receipt by Transmission Provider of the Interconnection Customer’s executed Interconnection Facilities Study Agreement, (C) At the end of the reporting quarter, the number of active valid Interconnection Service requests with ongoing incomplete Interconnection Facilities Studies where such Interconnection Requests had executed Interconnection Facilities Studies Agreement received by Transmission Provider more than ninety (90) or one hundred eighty (180) Calendar Days, as appropriate for that study, before the reporting quarter end, (D) Mean time (in days), for Interconnection Facilities Studies completed within Transmission Provider’s coordinated region during the reporting quarter, calculated from the date when Transmission Provider received the executed Interconnection Facilities Study Agreement to the date when Transmission Provider provided the completed draft Interconnection Facilities Study to the Interconnection Customer, (E) Percentage of delayed Interconnection Facilities Studies this reporting quarter, calculated as the sum of 3.5.2.3(B) plus 3.5.2.3(C) divided by the sum of 3.5.2.3(A) plus 3.5.2.3(C)).
Appears in 2 contracts
Sources: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)
Interconnection Facilities Studies Processing Time. (A) Number of Interconnection Requests that had Interconnection Facilities Studies that are completed within the Transmission Provider’s coordinated region during the reporting quarter and tendered to the Interconnection Customer in draft formquarter,
(B) Number of Interconnection Requests that had Interconnection Facilities Studies that are completed within the Transmission Provider’s coordinated region during the reporting quarter that were completed and tendered to the Interconnection Customer in draft form more than ninety (90) or one hundred and eighty (180) Calendar Days, as appropriate for that study, Days after receipt by the Transmission Provider of the Interconnection Customer’s executed Interconnection Facilities Combined Study Agreement,
(C) At the end of the reporting quarter, the number of active valid Interconnection Service requests with ongoing incomplete Interconnection Facilities Studies where such Interconnection Requests had executed Interconnection Facilities Studies Combined Study Agreement received by the Transmission Provider more than ninety (90) or one hundred and eighty (180) Calendar Days, as appropriate for that study, before the reporting quarter end,)
(D) Mean time (in days), for Interconnection Facilities Studies completed within the Transmission Provider’s coordinated region during the reporting quarter, calculated from the date when the Transmission Provider received the executed Interconnection Facilities Combined Study Agreement to the date when the Transmission Provider provided the completed draft Interconnection Facilities Study to the Interconnection Customer,
(E) Percentage of delayed Interconnection Facilities Studies this reporting quarter, calculated as the sum of 3.5.2.3(B3.5.1.3(B) plus 3.5.2.3(C3.5.1.3(C) divided by the sum of 3.5.2.3(A3.5.1.3(A) plus 3.5.2.3(C)3.5.1.3(C).
Appears in 1 contract
Sources: Standard Generator Interconnection Agreement (Sgia)