INTERCONNECTION COST. 13.1 The non-refundable and non-transferable Interconnection Application Fee to GEA covers only the application process for interconnection of each Qualifying System. Participant must pay the fee in advance when making application. Additional fees are payable to GEA in advance of expansion and/or transfer of the Qualifying System. If Participant has a solar PV and wind system at the same location, these are viewed as two separate Qualifying Systems. 13.2 Qualifying Systems equal to or less than 15kW - $500. 13.3 Qualifying Systems of 16kW – 50kW - $1000. 13.4 Qualifying Systems greater than 50kW – In the amount set forth on the attached exhibit. 13.5 Existing Qualifying System upgrade expansion - $150. 13.6 Existing Qualifying System transfer of property - $150.