Installation Timetable. The works specification submitted by the Contractor to the Customer shall include and specify the date(s) for: (a) completion of the design of the EPC Solutions; (b) commencement of the installation of the EPC Solutions; (c) progress claims to be made by the Contractor during the installation period, subject to achievement of the benchmarks to be identified in the works specification; and (d) completion of the installation and commissioning of the EPC Solutions (“contractual completion date”) which must be consistent with any corresponding dates identified in the DFS unless the Customer agrees otherwise.
Appears in 1 contract
Sources: Energy Performance Contract
Installation Timetable. The works specification submitted by the Contractor to the Customer shall include and specify the date(s) for:
(a) completion of the design of the EPC Solutions;
(b) commencement of the installation of the EPC Solutions;
(c) progress claims to be made by the Contractor during the installation period, subject to achievement of the benchmarks to be identified in the works specification; and
(d) completion of the installation and commissioning of the EPC Solutions (“contractual completion date”) which must be consistent with any corresponding dates identified in the DFS Quotation unless the Customer agrees otherwise.