Initial Contract Schedule Sample Clauses
Initial Contract Schedule. 5.1.1.1 Prior to the preconstruction meeting, CONTRACTOR shall furnish to PM/CM one hard copy and one copy in electronic format of an INITIAL CONTRACT SCHEDULE.
5.1.1.2 The INITIAL CONTRACT SCHEDULE shall be based on and incorporate the CONTRACT Milestone and Completion Dates specified in the CONTRACT DOCUMENTS.
5.1.1.3 The INITIAL CONTRACT SCHEDULE shall indicate the detailed plan for the work to be completed in the first ninety (90) days of the CONTRACT; details of planned mobilization of plant and equipment; sequence of early operations; and procurement of MATERIALS and equipment. WORK beyond ninety (90) days shall be shown in summary form.
5.1.1.4 The INITIAL CONTRACT SCHEDULE shall be a time-scaled, resource loaded Critical Path Method (CPM) type schedule, prepared in Primavera compatible software.
5.1.1.5 VERTICAL PROJECTS - The INITIAL CONTRACT SCHEDULE shall be cost loaded. The accepted cost loaded schedule will be used as a basis for monthly progress payments until acceptance of the CONTRACT SCHEDULE. Use of the INITIAL CONTRACT SCHEDULE for progress payments shall not exceed 30 days.
Initial Contract Schedule. No later than thirty (30) days after receiving Notice to Proceed, Contractor shall furnish to the District Representative three