Import Billing. The Developer shall be permitted to use 10% of the installed capacity for startup after inspection by the concerned officer of ESCOM and 115% of such energy provided by ESCOM for startup power shall be deducted from the energy pumped in to the grid by the Developer for determining the amount payable by ESCOM to the Developer. If energy over and above the requirement is drawn from the grid, the same shall be billed under the tariff applicable to HT industries demand charges.
Appears in 1 contract
Sources: Power Purchase Agreement
Import Billing. The Developer shall be permitted to use ten percent (10% %) of the installed capacity for startup after inspection by the concerned officer of ESCOM and one hundred and fifteen percent (115% %) of such energy provided by ESCOM for startup power shall be deducted from the energy pumped in to the grid by the Developer for determining the amount payable by ESCOM to the Developer. If energy over and other than the above the requirement is drawn from the grid, the same shall be billed under the tariff applicable to HT industries including demand charges.
Appears in 1 contract
Sources: Power Purchase Agreement
Import Billing. The Developer shall be permitted to use ten percent (10% %) of the installed capacity for startup after inspection by the concerned officer of ESCOM and one hundred and fifteen percent (115% %) of such energy provided by ESCOM for startup power shall be deducted from the energy pumped in to the grid by the Developer for determining the amount payable by ESCOM to the Developer. If energy over and above other than the above32 requirement is drawn from the grid, the same shall be billed under the tariff applicable to HT industries including demand charges.charges.33
Appears in 1 contract
Sources: Power Purchase Agreement