Guaranteed Substantial Completion Date. Contractor shall achieve Substantial Completion no later than the date specified in Attachment E (“Guaranteed Substantial Completion Date”). The Guaranteed Substantial Completion Date shall only be adjusted by Change Order as provided under this Agreement.
Appears in 5 contracts
Samples: Procurement and Construction Agreement (Corpus Christi Pipeline GP, LLC), Engineering, Procurement and Construction Agreement (Cheniere Energy Inc), Procurement and Construction Agreement (Cheniere Energy Inc)