Float. The progress schedule must show early and late completion dates for each task. The number of days between those dates will be designated as the “float.” Any float belongs to the Project and may be allocated by the Engineer to best serve timely completion of the Project.
Appears in 1 contract
Sources: Public Works Contract
Float. The progress schedule must shall show early and late completion dates for each task. The number of days between those these dates will shall be designated as the “float.” Any float belongs ”. The Float shall be designated to the Project and may shall be allocated by available to the Engineer to best serve timely completion of the ProjectCity as needed.
Appears in 1 contract
Sources: Construction Contract
Float. The progress schedule must show early and late completion dates for each task. The number of days between those these dates will be designated as the “float.” Any float belongs Float”. The Float will be designated to the Project and may will be allocated by available to both the Engineer City and the Contractor as needed to best serve timely completion of complete the ProjectWork in accordance with the Contract.
Appears in 1 contract
Sources: Agreement for Public Improvements
Float. The progress schedule must shall show early and late completion dates for each task. The number of days between those these dates will shall be designated as the “floatFloat.” Any float belongs The Float shall be designated to the Project and may shall be allocated by available to both the Engineer to best serve timely completion of Agency and the ProjectContractor as needed.
Appears in 1 contract
Sources: Construction Contract