Final Survey. The Company will deliver to TDF within 120 days after the date of Substantial Completion an update of the Survey, dated no earlier than the date of Substantial Completion, with a certification that no encroachments exist by the Improvements or on the Property other than those shown on the Survey and consented to, in writing, by TDF, and indicating the completed Improvements, the dimensions thereof at ground surface level, the distance therefrom to the facing exterior property lines and other buildings and any set-back lines, the location of access to the Project and all utility, water and other easements directly affecting the Project.