FACILITY TESTS. Contractor shall conduct the Availability Test and Functional Test for the Facility in accordance with Exhibit 25, and when Contractor believes that the Facility can satisfy the Minimum Capacity Level, Contractor shall conduct the Power Plant Controller Test and the Capacity Test in accordance with Exhibit 14B or Exhibit 14C, as applicable. Contractor shall submit a test report for each Facility Test within five (5) Days after the completion thereof, which test report shall include a summary of such Facility Test and the results for such test. Owner and Contractor will negotiate in good faith to agree upon detailed testing procedures that comply with the protocols set forth in Exhibit 14B, Exhibit 14C and Exhibit 25.