Exploration Stages Sample Clauses
Exploration Stages. 7.3.1 Within ten (10) Business Days of the Technical Committee voting to accept a Recommended Land Area for initial Exploration Work, and to the extent that the Company wishes to conduct Exploration Works under the Exploration Licenses, any necessary amendments to the work programme set out in such Exploration Licenses will be submitted for approval to MIMR pursuant to the Implementing Regulations.
7.3.2 With effect from:
(A) MIMR approving any amendments to the Exploration Licenses submitted in accordance with Clause 7.3.1 (Exploration Stages), to the extent any such amendments are necessary;
(B) the Company obtaining a Reconnaissance License or Exploration License issued by MIMR relating to the Additional Land Area (as applicable), to the extent there are any such Additional Land Areas; or
(C) the Technical Committee voting to accept a Recommended Land Area for initial Exploration Work, the Company will undertake initial Exploration Work in accordance with a reconnaissance exploration program (the “Exploration Program”) on the Recommended Land Area and any Additional Land Areas with the Typhoon™ Unit or such other exploration tools or techniques as the Technical Committee may approve (the “Generative Exploration Stage”). The Exploration Program will be subject to periodic review by the Technical Committee.
7.3.3 During the Exploration Phase, the Company shall undertake the initial Exploration Works in accordance with the Exploration Program until the Company identifies proposed target land areas on a Recommended Land Area or any Additional Land Areas for further, more invasive, Exploration Works (as applicable).
7.3.4 The Technical Committee shall periodically (and at least on a quarterly basis) review the data relating to the proposed target land areas and decide, by vote, to accept some or all of the identified target land areas for further Exploration Works (the “Exploration Drilling Stage”).
7.3.5 All other exploration works not captured in this Clause 7 (Exploration Phase) shall be determined and approved by the Technical Committee.
Exploration Stages. Within ten (10) Business Days of the Technical Committee voting to accept a Recommended Land Area for initial Exploration Work, and to the extent that the Company wishes to conduct Exploration Works under the Exploration Licenses, any necessary amendments to the work programme set out in such Exploration Licenses will be submitted for approval to MIMR pursuant to the Implementing Regulations.