Common use of Estimate Preparation Clause in Contracts

Estimate Preparation. Estimates shall be prepared consistent with the established project baseline and can be identified by each WBS element, or rolled up to cost account, Project Baseline Description (PBD), or total closure project level. The control system must maintain capability to provide Total Estimated Cost (TEC), Total Project Cost (TPC), Estimates-to-Complete (ETC), and Estimates-at Completion (EAC).

Appears in 2 contracts

Sources: Contract (Kaiser Group International Inc), Contract (Ch2m Hill Companies LTD)