Establishment of Queue Position in Interconnection System Impact Study Phase. Upon receipt of all items listed in Section 3.4.1 and verified by written acknowledgement by the Transmission Provider (Section 3.4.2), the Interconnection Request will be deemed valid and assigned a Queue Position in the Interconnection System Impact Study Phase. The Interconnection System Impact Study Phase Queue Position shall be based on the date that Interconnection Customer submitted a valid Interconnection Request (Section 4.1).
Appears in 3 contracts
Sources: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement