Energization Clause Samples
The Energization clause defines the process and conditions under which a facility, equipment, or system is first supplied with electrical power and becomes operational. Typically, this clause outlines the prerequisites that must be met before energization can occur, such as completion of safety checks, inspections, and regulatory approvals. For example, it may specify that all commissioning activities are finalized and relevant parties are notified prior to energizing the system. The core function of this clause is to ensure a safe, coordinated, and compliant transition to operational status, thereby minimizing risks associated with the initial application of electrical power.
POPULAR SAMPLE Copied 2 times
Energization. Consistent with the mutually acceptable procedures of the DeveloperRG&E and Connecting Transmission Owner, the DeveloperRG&E is responsible for the proper synchronizationenergization of the Large GeneratingTransmission Facility to the New York State Transmission System in accordance with NYISO and Connecting Transmission Owner procedures and requirements.
4.2 Real and Reactive Power Control and Primary Frequency Response. Power Factor Design Criteria.
Energization. In alignment with the reporting requirements in the CPUC’s Final Decision D.▇▇-▇▇-▇▇▇, SDG&E will provide biannual Energization Reports to the City.
Energization. Notwithstanding, the IPA may in its reasonable discretion designate a Quarterly Payment Cycle that includes a Quarterly Period that concludes on the month following Energization.
Energization. Company agrees to provide Electric Service as of the Commencement Date in accordance with the terms of the Energization Schedule set forth in Exhibit A-2.
Energization. Until energization has occurred with respect to all Blocks within Powered Shell-A, Landlord shall energize each Block concurrently with the occurrence of Phase Readiness for such Block. Landlord shall not be required to energize any Block achieving Phase Readiness in Powered Shell-B or Powered Shell-C (such Blocks, the “Energization Notice Blocks”) unless Tenant has delivered notice to Landlord that Tenant desires Landlord to energize any applicable Energization Notice Block(s) (an “Energization Notice”). If Tenant delivers an Energization Notice, then Landlord shall energize the applicable Energization Notice Block(s) no later than the date that is the later of (i) [***] days after Landlord’s receipt of Tenant’s Energization Notice or (ii) for each such Energization Notice Block, Phase Readiness for such Energization Notice Block. Notwithstanding anything herein to the contrary, energization of the Energization Notice Blocks pursuant to this Section 6.10 shall not be a condition to achievement of Commencement Date (Powered Shell-C), Commencement Date (Powered Shell-B), Upsize Rent Commencement Date or Substantial Completion.
Energization. Consistent with the mutually acceptable procedures of RG&E and Connecting Transmission Owner, RG&E is responsible for the proper energization of the Transmission Facility to the New York State Transmission System in accordance with Connecting Transmission Owner procedures and requirements.
Energization. As of the Closing Date, the H▇▇▇▇▇▇▇▇ Substation and the Populus Substation shall never have been energized to the bulk power electric transmission system; and
Energization. Neither the ISO nor the applicable Participating TO shall be obligated to energize, nor shall a Generating Unit (whether new or, if applicable, existing) be entitled to have its interconnection to the ISO Controlled Grid energized unless and until such Generating Unit has demonstrated to the ISO’s reasonable satisfaction that it has complied with or is capable of complying with all of the requirements of this Section 5.