Energisation Conditions Sample Clauses
Energisation Conditions. On or before the First Commissioning Sunset Date, Access Right Holder must use its best endeavours to ensure that:
(a) the Project is sufficiently completed to enable the Project to be connected to and energised from the Connection Point, and for commissioning of the Project to commence, safely and in compliance with applicable Law and Good Industry Practice;
(b) Access Right Holder (or its intermediary) has been registered as a “Generator” or “Integrated Resource Provider” (each as defined in the NER) with AEMO in relation to the Project and each unit in the Project is classified as a “scheduled generating unit”, “semi-scheduled generating unit”, “scheduled load” and/or “scheduled bidirectional unit” (as relevant, each as defined in the NER); and
(c) Access Right Holder has satisfied or delivered, all Social Licence Commitments required prior to First Commissioning, (each an “Energisation Condition”).).
Energisation Conditions. On or before the First Commissioning Sunset Date, Access Right Holder must use its best endeavours to ensure that:
(a) the Project is sufficiently completed to enable the Project to be connected to and energised from the Connection Point, and for commissioning of the Project to commence, safely and in compliance with applicable Law and Good Industry Practice;
(b) Access Right Holder (or its intermediary) has been registered as a “Generator” or “Integrated Resource Provider” (each as defined in the NER) with AEMO in relation to the Project and each unit in the Project is classified as a “scheduled generating unit”, “semi-scheduled generating unit”, “scheduled load” and/or “scheduled bidirectional unit” (as relevant, each as defined in the NER); and
Energisation Conditions. On or before the Commissioning Readiness Sunset Date, Access Right Holder must use its best endeavours to ensure that:
(a) the Project is sufficiently completed to enable the Project to be connected to and energised from the Connection Point, and commissioning of the Project to commence, safely and in compliance with applicable Law;
(b) Access Right Holder (or its intermediary) has been registered as a “Generator” or “Integrated Resource Provider” (as defined in the NER) with AEMO in relation to the Project and each unit in the Project is classified as a “scheduled generating unit”, “semi-scheduled generating unit”, “scheduled load” and/or “scheduled bidirectional unit” (as relevant, each as defined in the NER);
(c) any other requirements that Access Right Holder is responsible for satisfying under the ESCD before the Project (or relevant part of it) is able to be connected to and energised from the Connection Point, and commissioning of the Project is able to commence, have been satisfied; and
(d) Access Right Holder has satisfied or delivered, all Social Licence Commitments required prior to Commissioning Readiness, (each an “Energisation Condition”).