Effect of variations in MSW Quality. 17.6.1 If the C&D waste delivered to the Project Site is more than 25% for 15 consecutive days, the Concessionaire has the right to reject the C&D waste in excess of 25%. The Lead ULB will be responsible to dispose the excess C&D waste at its own cost. However, the amount of excess C&D delivered to the Project Site will be deducted from the quantity of MSW delivered in the next 7 days.
Appears in 1 contract
Sources: Concession Agreement
Effect of variations in MSW Quality.
17.6.1 If the C&D waste delivered to the Project Site is more than 25% for 15 consecutive days, the Concessionaire has the right to reject the C&D waste in excess of 25%. The Lead ULB will be responsible to dispose the excess C&D waste at its own cost. However, the amount of excess C&D delivered to the Project Site will be deducted from the quantity of MSW delivered in the next 7 days.
Appears in 1 contract
Sources: Concession Agreement
Effect of variations in MSW Quality.
17.6.1 17.4.1 If the C&D waste delivered to the Project Site is more than 25% for 15 consecutive days, the Concessionaire has the right to reject the C&D waste in excess of 25%. The Lead ULB will be responsible to dispose the excess C&D waste at its own cost. However, the amount of excess C&D delivered to the Project Site will be deducted from the quantity of MSW delivered in the next 7 days.
Appears in 1 contract
Sources: Concession Agreement