Each Final Commissioning. Programme shall describe the steps necessary, the party responsible for taking each of such steps and the timing and sequence of each of such steps to ensure:
(a) that Project Co's Pre-Completion Commissioning will not delay the Phase 1 Actual Completion Date and/or the Phase 2 Actual Completion Date and/or the Phase 3 Actual Completion Date (as appropriate) from occurring by the Completion Dates; and
(b) that Project Co's Post Completion Commissioning and the Board's Post Completion Commissioning is completed by the relevant Commissioning End Dates.